Departments

Redlands 311 App

Report Graffiti, Potholes, Illegal dumping and more!

Under Design/Planned

Wabash Avenue Water Pipeline Replacement Project

Replacement of water pipelines and appurtenances along Wabash Avenue. The work shall consist of all traffic control (including furnishing and installing all arrowboards, barricades, signs, delineators, and flagmen); all utility location and verification (excavating, exposing, and verifying top, bottom, and side of utility facilities); all pavement removal and disposal; all earthwork (including trenching, shoring, sloping, bedding, and backfilling including select imported material or select native material); compacting; furnishing and installing all pipe, fittings, and appurtenances; protecting in place or removing and replacing all existing utilities, trees, and public and private improvements; replacing all asphalt concrete pavement including asphalt concrete overlays; pavement striping restriping; testing and disinfecting all pipelines; replacing destroyed survey monuments; disposing of excess soil and rock material and restoring all areas and improvements to pre-construction conditions.

Expected Completion Date: January 2015

Ward Way Reservoir Recoating and Improvement Project

This project consists of reservoir improvements which include rehabilitation of the reservoir and the addition of necessary supplemental features.  Upon completion, the project will increase the reliability of your water system, increase water quality, and increase the longevity of this reservoir.

Expected Completion Date: June 2015

2014 CIP Water Pipeline Replacement Project

Replacement of water pipelines and appurtenances at various locations throughout the City. The work shall consist of all traffic control (including furnishing and installing all arrowboards, barricades, signs, delineators, and flagmen); all utility location and verification (excavating, exposing, and verifying top, bottom, and side of utility facilities); all pavement removal and disposal; all earthwork (including trenching, shoring, sloping, bedding, and backfilling including select imported material or select native material); compacting; furnishing and installing all pipe, fittings, and appurtenances; protecting in place or removing and replacing all existing utilities, trees, and public and private improvements; replacing all asphalt concrete pavement including asphalt concrete overlays; pavement striping restriping; testing and disinfecting all pipelines; replacing destroyed survey monuments; disposing of excess soil and rock material and restoring all areas and improvements to pre-construction conditions.

Expected Completion Date: June 2015

Texas Street Reservoir Non-Potable Booster Station

The City intends to construct the new facility at its existing Texas Street Reservoir complex.  The Texas Street Reservoir facility is located near the intersection of West Pennsylvania Avenue and Texas Street in Redlands, California.  The facility consists of the 1 MG Texas Street Reservoir, potable water pump station, GAC treatment facility, two groundwater wells, and non-potable water reservoirs and booster pump station.  As part of the Project, the existing non-potable reservoirs and booster pump stations will be demolished.

Expected Completion Date: June 2015

Bid and Award

There are no water projects under bid and award at this time.

Under Construction

'B' Contract - Iowa Street to Nevada Street Pipeline Rehabilitation Project

Rehabilitation of a non-potable water pipeline and appurtenances north of Barton Road between Iowa Street and Nevada Street. The scope of work for this project is the installation of 615 linear feet of 20" PVC pipe adjacent to the existing pipe in the southeast portion of Heritage Park.

The work shall consist of all traffic control (including furnishing and installing all arrowboards, barricades, signs, delineators, and flagmen); all utility location and verification (excavating, exposing, and verifying top, bottom, and side of utility facilities); all earthwork (including trenching, shoring, sloping, bedding, and backfilling including select imported material or select native material); compacting; furnishing and installing all pipe fittings, and appurtenances; verifying pipe alignment; protecting in place or removing and replacing all existing utilities, trees, and public and private improvements; testing and disinfecting all pipelines; replacing destroyed survey monuments; disposing of excess soil and rock material and restoring all areas and improvements to pre-construction conditions.

Expected Completion Date: June 2014

Fern Avenue & San Timoteo Canyon Road Water Pipeline Replacement

Replacement of water pipelines and appurtenances along Fern Avenue and San Timoteo Canyon Road. The scope of work for this project is the installation of 12” pipeline and 8" pipeline.

The work shall consist of all traffic control (including furnishing and installing all arrowboards, barricades, signs, delineators, and flagmen); all utility location and verification (excavating, exposing, and verifying top, bottom, and side of utility facilities); all pavement removal and disposal; all earthwork (including trenching, shoring, sloping, bedding, and backfilling including select imported material or select native material); compacting; furnishing and installing all pipe, fittings, and appurtenances; protecting in place or removing and replacing all existing utilities, trees, and public and private improvements; replacing all asphalt concrete pavement including asphalt concrete overlays; pavement striping restriping; testing and disinfecting all pipelines; replacing destroyed survey monuments; disposing of excess soil and rock material and restoring all areas and improvements to pre-construction conditions.

Expected Completion Date: July 2014 

2013 CIP Water Pipeline Replacement Project - Phase 2

Replacement of water pipelines and appurtenances at 15 locations throughout the City. The scope of work for this project is the installation of approximately 14,300 linear feet of 8” pipeline, 1,000 linear feet of 12" pipeline and 2,500 linear feet of 16" pipeline.

The work shall consist of all traffic control (including furnishing and installing all arrowboards, barricades, signs, delineators, and flagmen); all utility location and verification (excavating, exposing, and verifying top, bottom, and side of utility facilities); all pavement removal and disposal; all earthwork (including trenching, shoring, sloping, bedding, and backfilling including select imported material or select native material); compacting; furnishing and installing all pipe, fittings, and appurtenances; protecting in place or removing and replacing all existing utilities, trees, and public and private improvements; replacing all asphalt concrete pavement including asphalt concrete overlays; pavement striping restriping; testing and disinfecting all pipelines; replacing destroyed survey monuments; disposing of excess soil and rock material and restoring all areas and improvements to pre-construction conditions.

Expected Completion Date: November 2014

Agate #1 Well & Equipment Rehabilition Project (Project No. 71252)

The City owns Agate 1 Well which is located on the corner of Agate Avenue and Mentone Blvd. in the town of Mentone. A vehicle collided with the well in the summer of 2013. To determine the extent of the damage the well and column was pulled and a camera was used to video the condition of the well. The video showed that well was constructed with mill knife louvers which allowed excessive sand intrusion and had normal tuberculation for its age. No other issues were found with the well casing. Excessive sand intrusion was confirmed by examination of the pump bowls. The City would like to continue to utilize the well and has determined the best option is to reline the existing well with a 16" liner and use a gravel packing of sufficient size for the sand conditions. This well must be in operation prior to the summer demand as source waters are expected to be at a minimum.

Expected Completion Date: June 2014

Highline Water Main Replacement Project (Project No. 71325)

This project is limited to the replacement of approximately 14,785 L.F. of water pipeline including all fittings, valves, water services, hydrants, and appurtenances, providing traffic control, performing utility location and verification (excavating, exposing, and verifying top, bottom, and side of utility facilities); all pavement removal and disposal, all earthwork (including trenching, material or select native material), compacting, protecting in place or removing and replacing all existing utilities, trees, and public and private improvements; replacing all asphalt concrete pavement including asphalt concrete overlays, pavement striping, restriping; testing and disinfecting all pipelines; replacing destroyed survey monuments; disposing of excess soil and rock material and restoring all areas and improvements to pre-construction conditions.

Expected Comletion Date: July 2014

Water Distribution SCADA System Upgrade

The proposed work shall be performed in accordance with the plans, specifications and other contract documents and shall consist of the following: installation of SCADA system upgrades at the City’s Highland Avenue Water Complex (HAWC), Horace P. Hinckley Water Treatment Plant, Sunset Reservoir, Texas
Grove Reservoir, and procurement of SCADA HMI system software and hardware. Up to thirteen (13) additional reservoir sites may be added to the scope of work.

The Contractor shall, upon completion of the SCADA System Upgrade installation shall provide all “as-built” documentation for the electrical systems for all sites in the project. The contractor shall support the City Engineer for the Final System acceptance testing prior to filing Notice of completion. 

Expected Completion Date: April 2014

Capital Improvement Program: Optimization of Horace P. Hinckley Water Treatment Plant

The work for this project consists of improvements to major parts of Hinckley and Agate Reservoir including the 1) Influent Meter and Mixing Structure; 2) Flocculation and Settling Basin; 3) Filter; 4) Waste Washwater Recovery Basin; 5) Packaged Water Treatment System 6) Sludge Lagoons; 7) Chemical Feed and Storage System 8) Agate Reservoir and Blending System 9) Electrical and Instrumentation and Control Work; and 10) Yard piping and structures.

Expected Completion Date: 2014 

Completed

Water Services Replacement 2013 Project No. 71249

This project includes replacement of 254 existing water service lines including all fittings and appurtenances, meter boxes, providing traffic control, performing utility location and verification, all earthwork (including trenching, material or select native material), compacting, protecting in place all existing utilities, trees, and public and private improvements, disinfecting all service lines; disposing of excess soil and rock material and restoring all areas and improvements to preconstruction conditions.

Project Completion Date: 5/13/14

Total Cost of the Project: $300,000.00

Dearborn Reservoir Roof Rehabilitation

Reservoir rehabilitation shall include reinforced concrete drop panels, column jackets, and column footings; concrete roof slab rehabilitation, slab pour strip repairs, crack repairs, fiber reinforcement strips and coatings over columns; adding an interior concrete curb at the interface of the wall and floor; and repairing/rehabilitation of the expansion joint beam.

Project Completion Date: 5/13/14

Total Cost of the Project: $1,484,863.69

Reservoir Recoating and Improvement Project, Arroyo Reservoir

This project includes complete removal of the existing interior and exterior tank coatings. New interior and exterior coating will be applied. The tank improvements include a new spiral staircase, new hatch opening, new handrails, new mixing system, and a new rain gutter and downspout system. The cathodic protection system will also be removed and replaced.

Project Completion Date:5/28/14

Total Cost of the Project: $443,316.50

2013 CIP Water Pipeline Replacement Project-Phase 1 (Project No. 71243)

Replacement of water pipelines and appurtenances at 5 locations throughout the City. The scope of work for this project is the installation of 8,246 linear feet of 8" pipeline and the resurfacing of selected streets and associated concrete work.

Project Completion Date: 1/16/14

Total Cost of the Project: $1,644,838.60

Country Club Booster Station Electrical and Yard Piping

Demolition and replacement of an existing booster station utilizing an innovative submerged pump design. Three submerged pumps will be installed with a bay for a future pump; associated underground and surface piping; multiple flow meters; Lighting, electrical system upgrades and SCADA work (remote data acquisition); site drainage and pavement replacement. Design was significantly revised to include a new reservoir overflow drainage system conveyed offsite for both reservoirs.

Project Completion Date: 6/3/13

Total Cost of the Project: $956,137.96

2012 Capital Improvement Program Water Pipeline Replacement Project (Project No. 71206)

Replacement of water pipelines that are substandard, deteriorated and undersized, which are not economical to repair.

Project Completion Date: 12/11/13

Total Cost of the Project: $5,715,380.00

Brookside Avenue Water Pipeline Replacement Project (Project No. 71234)

Replacement of water pipelines that are substandard and deteriorated, which are not economical to repair.

Project Completion Date: 8/23/2013

Total Cost of the Project: $289,660.00

Mira Monte Drive Water Pipeline Replacement Project (Project No. 71247)

Replace approximately 685 linear feet of water pipelines that are substandard, deteriorated and undersized, which are not economical to repair.

Total Cost of the Project: $144,556.00

Brookside Ave. & Ash St. Water Pipeline Replacement Project (Project No. 71241)

The scope of work for this project includes, but is not limited to, installation of approximately 1,130 linear feet of 12" DIP pipelines, 630 linear feet of 8" DIP pipelines, 50 linear feet of CML&C pipelines and appurtenances, 3 fire hydrants, reconnection of 30 services, tie-in to existing lines, grind & overlay, and re-striping and pavement markings.

Total Cost of the Project: $362,802.95

Soffel Avenue Water Pipeline Replacement Project (Project No. 71239)

Replacement of water pipelines that are substandard and deteriorated, which are not economical to repair.

Project Completion Date: 8/15/2013

Total Cost of the Project: $374,859.11 (with all change orders)

Fifth Avenue Pipeline Replacement Project

Replacement of water pipelines that are substandard, deteriorated and undersized, which are not economical to repair.

Total Cost of the Project: $197,277.02

Construction Completed: November 30, 2012 (Waterline Only)

To Search Our Site

Use google search
with the site option.

site:cityofredlands.org your text
 

PARIS

            

City Calendar

City Hall is closed every
other Friday.  Check the
calendar for closed Fridays.

2014 City Hall Calendar

City Hall Hours:
7:30 am to 5:30 pm

Events Calendar

 

Upcoming

Yesterday

  1. Chinese Story Time
    • Start time: 05:45pm
    • End date: Tuesday, July 29th
    • End time: 06:15pm
    • Join us in the Story corner of the Young Readers' Room for Chinese/Mandarin songs and stories.

    • View this event in Google Calendar

Today

  1. Preschool Story Time
    • Start time: 10:15am
    • End date: Wednesday, July 30th
    • End time: 10:45am
    • Come join in the fun of stories and songs and meet new friends! Join us in the Assembly Room each Wednesday morning at 10:15 a.m.

    • View this event in Google Calendar
  2. Post 261 Explorer Meeting
    • Start time: 06:30pm
    • End date: Wednesday, July 30th
    • End time: 08:30pm
    • Open Enrollment to join the Redlands Explorer Program is in January of every year, but you can pick-up and drop-off applications through-out the entire year at the Fire Administration office. Ages to join are between 15 years To 21 years old.

      Fire Administrative Office
      35 Cajon Street #12
      Redlands, CA 92373

    • View this event in Google Calendar

Tomorrow

  1. Tiny Tot Story Time
    • Start time: 10:40am
    • End date: Thursday, July 31st
    • End time: 10:55am
    • Join us in the Assembly Room each Thursday morning for great songs, and stories!

    • View this event in Google Calendar
  2. Market Night
    • Start time: 06:00pm
    • End date: Thursday, July 31st
    • End time: 09:00pm
    • Established in 1988, Redlands Market Night has established itself as one of the most successful certified farmers markets in Southern California! Vendors vie to participate in the event that has attracted thousands of weekly visitors since its inception. Visitors are welcomed into an inviting atmosphere complete with lighted trees, brick sidewalks, historic buildings, and great musical entertainment. Crowds are pleasantly surrounded by over 150 food and merchandise booths, not to mention the downtown shopkeepers, every Thursday night.

    • View this event in Google Calendar

Friday, August 1st

  1. City Hall Closed
    • Extended service hours are offered in order for the public to conduct City business before and after traditional business hours. City staff is available 9 hours a day to serve you. City Hall offices are closed every other Friday.

    • View this event in Google Calendar

Saturday, August 2nd

  1. Celebration of Healthy Living - Saturday Morning Farmers' Market
    • Start time: 08:00am
    • End date: Saturday, August 2nd
    • End time: 12:00pm
    • To kick off the City's new SNAP/EBT electronic benefits capability at the Saturday Morning Farmers' Market and as part of the City’s Healthy Redlands initiative, the City of Redlands is sponsoring a Celebration of Healthy Living at the Saturday Morning Farmers' Market in Ed Hales Park from 8 a.m. to noon Saturday, Aug. 2.

      This free event will include composting with worms, gardening and water conservation demonstrations; cooking demonstrations; information on healthy nutrition, physical activity, and health care programs; as well as free face-painting for kids, games and prizes. The Saturday Farmers' Market is located in the City parking lot adjacent to Ed Hales Park south of Redlands Boulevard between Fifth and Sixth streets.

      Presentations on the stage at Ed Hales Park will include:

      Zumba Fitness for Adults at 8:45 a.m.
      Zumba Fitness for Youth at 9:30 a.m.
      Tai Chi at 10:15 a.m.
      Tumbling for Fun at 11 a.m.

      Free shuttle service will be available every 30 minutes from the Redlands Community Center at 111 W. Lugonia Ave. to the Farmers Market.

      Additional participants and presenters include:

      The Cooking Block - Cooking Classes and C.E.N.T.E.R. Management Program
      UCCE Master Gardener Demonstrations - Container Herb Gardening and Vermi-composting (composting with worms!)
      San Bernardino Master Food Preservers
      Molina Health Care - Managing Your Health Care Needs
      YMCA of the East Valley - Youth Development and Healthy Living Programs
      Redlands Community Hospital - Health Education Programs
      Building A Generation - Family Resource Center
      Social Action Community Health Services - Low Cost Health Care Programs
      IEHP - Super Hero Nutricia Fighting Childhood Obesity!
      County of San Bernardino - Children & Family Services Programs
      City of Redlands - Water Efficient Gardening
      County of San Bernardino - Nutrition Programs
      County of San Bernardino - Transitional Assistance Department-SNAP/EBT
      City of Redlands - Saturday Morning Farmers’ Market
      County of San Bernardino - Women, Infants and Children (WIC) Program

    • View this event in Google Calendar
  2. Household Hazardous Waste Collection site
    • Start time: 09:30am
    • End date: Saturday, August 2nd
    • End time: 12:30pm
    • During operating hours, residents can dispose of household materials including, outdated prescription medication (with the exception of controlled substances), outdated pet prescription medication, paint products, chemical cleaners, pesticides, fertilizers, hobby/pool supplies, automotive oil, filters, brake fluid, transmission fluid, anti-freeze, gasoline, and propane tanks.

      The site does not accept business waste, radioactive wastes, medical waste, explosives, reactives, or asbestos.

    • View this event in Google Calendar
  3. Spanish Story Time
    • Start time: 10:15am
    • End date: Saturday, August 2nd
    • End time: 10:45am
    • Join us in the story corner of the Young Readers' Room and enjoy stories and songs in Spanish!

    • View this event in Google Calendar

Monday, August 4th

  1. Environmental Review Committee
  2. Tango classes
    • Start time: 06:45pm
    • End date: Monday, August 4th
    • End time: 08:00pm
    • Tango Classes to begin at the Redlands Community Center

      Come and enjoy tango lessons in a comfortable and fun setting. Tango lessons will be taught on Mondays beginning Aug. 4 through Aug. 25. Class runs from 6:45 to 8 p.m. Registration fee is $8 per person; partners are not required.

      Space is limited, so sign up today at the Redlands Community Center or online at www.cityofredlands.org/recreation/classes. For more information, please call Joe Sidor at (909) 792-6076.

      All classes are held at the Redlands Community Center multipurpose room. The Redlands Community Center is located at 111 W. Lugonia Ave. For more information, please call the Redlands Community Center at (909) 798-7572.

    • View this event in Google Calendar

Tuesday, August 5th

  1. Summer Reading Program #7
    • Start time: 01:00pm
    • End date: Tuesday, August 5th
    • End time: 02:00pm
    • Our final act of the summer will be One World, One Rhythm. Join us in the Contemporary Club for a musical adventure with these great musicians.

    • View this event in Google Calendar
  2. Summer Reading Program Finale
    • Start time: 02:00pm
    • End date: Tuesday, August 5th
    • End time: 03:00pm
    • The In-N-Out Food Truck will be here for our Grand Finale to serve lunch to all of our Summer Reading participants. This will be a first come, first serve event. There will be a grilled cheese sandwich option for those who are vegetarians.

    • View this event in Google Calendar
  3. City Council Closed Session Meeting
    • Start time: 05:00pm
    • End date: Tuesday, August 5th
    • End time: 06:00pm
    • Agenda available to view at http://cityofredlands.org/councilvideo

    • View this event in Google Calendar
  4. Chinese Story Time
    • Start time: 05:45pm
    • End date: Tuesday, August 5th
    • End time: 06:15pm
    • Join us in the Story corner of the Young Readers' Room for Chinese/Mandarin songs and stories.

    • View this event in Google Calendar
  5. City Council Meeting
    • Start time: 06:00pm
    • End date: Tuesday, August 5th
    • End time: 08:00pm
    • Agenda available to view at http://cityofredlands.org/councilvideo

    • View this event in Google Calendar

Wednesday, August 6th

  1. Preschool Story Time
    • Start time: 10:15am
    • End date: Wednesday, August 6th
    • End time: 10:45am
    • Come join in the fun of stories and songs and meet new friends! Join us in the Assembly Room each Wednesday morning at 10:15 a.m.

    • View this event in Google Calendar
  2. Post 261 Explorer Meeting
    • Start time: 06:30pm
    • End date: Wednesday, August 6th
    • End time: 08:30pm
    • Open Enrollment to join the Redlands Explorer Program is in January of every year, but you can pick-up and drop-off applications through-out the entire year at the Fire Administration office. Ages to join are between 15 years To 21 years old.

      Fire Administrative Office
      35 Cajon Street #12
      Redlands, CA 92373

    • View this event in Google Calendar

Thursday, August 7th

  1. Tiny Tot Story Time
    • Start time: 10:40am
    • End date: Thursday, August 7th
    • End time: 10:55am
    • Join us in the Assembly Room each Thursday morning for great songs, and stories!

    • View this event in Google Calendar
  2. Historic and Scenic Preservation Commission
  3. Market Night
    • Start time: 06:00pm
    • End date: Thursday, August 7th
    • End time: 09:00pm
    • Established in 1988, Redlands Market Night has established itself as one of the most successful certified farmers markets in Southern California! Vendors vie to participate in the event that has attracted thousands of weekly visitors since its inception. Visitors are welcomed into an inviting atmosphere complete with lighted trees, brick sidewalks, historic buildings, and great musical entertainment. Crowds are pleasantly surrounded by over 150 food and merchandise booths, not to mention the downtown shopkeepers, every Thursday night.

    • View this event in Google Calendar

Friday, August 8th

  1. Guan Fei art exhibition
    • Start time: 01:00pm
    • End date: Friday, August 8th
    • End time: 05:00pm
    • The A. K. Smiley Public Library, in cooperation with the California Center for Culture and Arts, will host a three-day exhibition of paintings by renowned artist Guan Fei from 1 to 5 p.m. Aug. 8-10.

      Born in Qingdao, China, Guan Fei began his artistic studies at the School of Arts and Crafts in Qingdao. In 2011, Guan graduated from the prestigious Central Academy of Fine Arts in Beijing, China.

      Although he has had several exhibitions in China, this will be his first in the United States. In 2013, Guan spent several months in Redlands, developing a deep admiration for the community. During his visit he was inspired to paint a beautiful new series of landscapes and building portraits entitled Redlands: Southern California's Village of Orange Groves. Twenty of these works will be featured at the Smiley Library’s exhibit.

      Through a translator Guan stated that the exhibit is an expression of the love he has developed for Redlands. “The theme of the exhibit is ‘Smile and Embrace.’ The name Smiley is so similar to smile, and the community has embraced me and I desire to return that affection.”

      "Guan Fei’s passion for our town is readily apparent in his work," commented Library Director Don McCue. "I'm certain our patrons will enjoy his depictions of some of Redlands’ landmark buildings and impressive landscapes".

      The A.K. Smiley Public Library is located at 125 W. Vine St. in Redlands. For further information please consult the library's website www.akspl.org or call 909-798-7565.

    • View this event in Google Calendar

Login page here.