Guidelines for Solar Plan Submittal

Post

For roof mounted PV arrays, sized 10 kW AC and less, and not including a battery back-up compnent: These types of submittals will be reviewed over the counter, and building permits can be issued on the same day.  Structural engineering calculations are not required for issuance of a photovoltaic permit for single family residences.  An Eligibility Checklist for Expedited Solar Photovoltaic Permitting shall be completed prior to the solar plan review.
Eligibility Checklist for Expedited Solar Photovoltaic Permitting

For roof mounted PV arrays, sized greater than 10 kW AC:  These types of submittals will be taken in for plan review, with a 10 business day turn-around. 

For ground mounted PV arrays: These types of submittals will be taken in for plan review, with a 10 business day turn-around.  Structural engineering calculations are required, indicating required footings and solar panel required bolting.